Tak este jeden clanok aj s konkretnymi cislami: Smith has also heard that some of the biggest bike brands are buying up as much factory space as possible, further complicating the situation for smaller brands trying to catch up. A lot of competing brands share the same production factories overseas and have to book frame manufacturing time far in advance. [...] Major component brands such as Shimano, SRAM, Fox, and Schwalbe, who produce mainly in Taiwan, give lead times of between 9 and 18 months. They are normally able to deliver within a maximum of 3 months.” They credited sourcing of raw materials as complicating the issue. [...] Commencal has also experience shipping issues. “A concrete example, it took us about 3 weeks to ship a container from Taiwan to Golden, Colorado, but now we need between 2 and 3 months. The ports are full.” https://www.singletracks.com/mtb-news/supply-chains-are-kinked-extended-making-it-more-difficult-to-get-a-new-mountain-bike-again/ |
| |||||||||||||||||||||||